Ultrasound commissioning checks help during startup after a shutdown by catching the problems that shutdown work leaves behind: passing valves, leaking flanges, failed steam traps, dry or over-greased bearings, cavitating pumps, and electrical arcing. An ultrasound instrument hears the high-frequency friction and turbulence these faults make, often before heat or vibration shows anything. The checks are fast, non-invasive, and run while the plant comes back online.

This guide walks through 9 steps for using ultrasound before, during, and after a restart. It also includes a comparison with other startup checks, a sample commissioning register, and a simple way to turn every reading into a tracked baseline.

Key Takeaways

  • Baseline before you shut down: Readings taken on the last healthy day give you a reference point for every startup check.
  • Use four startup windows: Plan ultrasound checks for before shutdown, during isolation, during warm-up, and at first run under load.
  • Hear faults before they heat up: Ultrasound flags leaks, trap failures, poor lubrication, and arcing earlier than most other startup checks.
  • Save the new baseline: Readings from a clean startup become the reference for every inspection route that follows.

Step 1: Plan Ultrasound Commissioning Around Four Startup Windows

Four-window ultrasound commissioning timeline: before shutdown, isolation, warm-up, first run | Cryotos

Good ultrasound commissioning starts with a plan that matches checks to the moment they matter. A shutdown has natural windows, and each one suits a different ultrasound test.

Ultrasound commissioning is the use of ultrasound checks to confirm equipment is sound during startup. The instrument detects sound above about 20 kHz and converts it into an audible signal and a decibel reading. It sits alongside vibration analysis and infrared as a core condition monitoring technique. ISO 29821 covers ultrasound for condition monitoring, and ISO 18436-8 sets inspector qualification levels.

The Four-Window Startup Ultrasound Method:

  • Window 1, Before Shutdown: Record dB readings and sound files on critical assets while they still run normally.
  • Window 2, During Isolation: Check that isolation valves hold, and that enclosures are tight before work and before reassembly sign-off.
  • Window 3, Warm-Up and Re-Pressurization: Scan joints, seals, and steam traps as pressure and temperature return.
  • Window 4, First Run Under Load: Listen to bearings, pumps, valves, and electrical gear once equipment reaches normal speed and load.

Ultrasound never replaces formal energy isolation. OSHA's lockout/tagout standard (29 CFR 1910.147) still governs every isolation and re-energization step. Ultrasound adds evidence; it does not sign off safety.

Step 2: Capture Ultrasound Baselines Before the Shutdown Starts

The most useful startup reading is one you can compare against something. Take baselines on critical assets in the days before the shutdown, while they run at normal load and temperature.

What to record on each critical asset

  • dB reading: Take it at a marked test point with the same sensor, frequency, and sensitivity every time.
  • Sound file: Save a short recording so you can listen for changes in tone, not just level.
  • Operating context: Note speed, load, pressure, and temperature at the time of the reading.
  • Known issues: Flag assets already running noisy, so you know which ones the shutdown should fix.

Most maintenance teams skip this step because the shutdown plan is already crowded. Yet without a baseline, a startup reading only tells you "loud" or "quiet," not "better" or "worse."

Ten minutes per critical asset before shutdown saves hours of guessing after startup.

Want to know what one failed restart costs your plant? Put a number on it with the unplanned downtime calculator.

Step 3: Confirm Valve Isolation and Leak Tightness During the Shutdown

Valve leak-by is the flow of fluid through a valve that should be fully closed. Isolation valves that pass fluid are a common shutdown hazard. Ultrasound in contact mode hears the turbulence of fluid squeezing past a closed seat, which helps teams find a passing valve before work starts behind it.

How to check a closed valve with ultrasound

  • Take an upstream reading: Touch the pipe a short distance before the valve to set the reference level.
  • Read at the seat: Touch the valve body over the seat, where leak-by turbulence is loudest.
  • Read downstream: Touch the pipe just after the valve. A downstream reading at or below upstream suggests the seat is holding.
  • Confirm by procedure: If a valve sounds like it is passing, treat the isolation as unproven and follow your site procedure for double block and bleed or other proof.

Testing tightness with an ultrasonic tone generator

Some systems cannot be pressurized for a leak test. An ultrasonic tone generator placed inside a tank, cabinet, heat exchanger shell, or door seal fills the space with ultrasound. An inspector scans the outside, and any gap leaks sound to the instrument.

This lets you check hatches, gaskets, and seals before closing up, when fixing them still costs minutes rather than a second shutdown.

Step 4: Leak-Check Flanges, Seals, and Joints During Re-Pressurization

Every flange, union, and fitting opened during a shutdown is a possible leak on restart, which makes leak checks a core part of ultrasound commissioning. Scan them as pressure comes back, in stages if your procedure allows, so leaks are found at low pressure rather than full pressure.

  • Scan in airborne mode: Set the instrument near 38 to 40 kHz and sweep each disturbed joint for the rushing sound of escaping gas or steam.
  • Work from a joint list: Use the shutdown work list to find every joint that was broken, so none are missed.
  • Tag and record: Tag each leak, note its size class, and decide whether to fix it now or monitor it.
  • Re-scan after tightening: A fixed leak should go quiet. A softer but still present sound means the fix is partial.

Compressed air, nitrogen, and steam leaks are easy to hear with ultrasound even in a noisy plant, because most machinery noise sits in the audible range. Liquid leaks are harder to hear and often need visual checks as well.

Finding leaks at re-pressurization is far cheaper than finding them after insulation is back on.

Step 5: Commission Steam Traps as the System Warms Up

Steam traps work hardest during warm-up, when cold pipes produce large amounts of condensate. That makes startup the right time to confirm every steam trap works as designed.

What a healthy trap sounds like on startup

  • Inverted bucket and thermodynamic traps: Listen for a clear open-and-close cycle with quiet spells between discharges.
  • Float and thermostatic traps: Listen for a steady, modulating flow that rises and falls with condensate load.
  • Blowing-through trap: A constant loud rush on an intermittent trap suggests it is stuck open and passing live steam.
  • Blocked or cold trap: Silence plus a cold inlet points to a plugged strainer, a closed valve, or an air-bound trap.

Pair each reading with a temperature check using an infrared thermometer or thermography. Ultrasound tells you how the trap is cycling, and temperature tells you whether condensate is backing up.

Re-test traps once the system reaches steady temperature, because warm-up loads can mask a trap that fails under normal running.

Step 6: Verify Bearing Lubrication and Rotating Equipment at First Run

Grease-by-ear bearing lubrication process using ultrasound at first run | Cryotos

Bearings are often re-greased, replaced, or disturbed during a shutdown. Ultrasound hears friction inside a bearing directly, which makes it one of the best first-run checks on motors, pumps, fans, and gearboxes.

  • Compare against the baseline: Read each bearing at the same test point and settings used before the shutdown.
  • Watch for a rise: Many programs use a rise of about 8 dB over baseline as a sign that a bearing needs attention, often lubrication. Set your own limits from site data.
  • Grease by ear: Add grease slowly while listening. Stop when the reading drops and holds. A reading that climbs again means you are over-greasing.
  • Listen to the tone: Crackling, clicking, or rubbing sounds point to damage, rubbing guards, or misaligned couplings left from the shutdown.

Ultrasound works well at low speeds where vibration data is weak, such as slow conveyors and mixers. For higher-speed machines, pair it with vibration readings for a fuller picture.

A bearing that passes its ultrasound commissioning check at first run is one less surprise in the first week of production.

Step 7: Listen for Cavitation, Recirculation, and Passing Valves Under Load

Once flow returns, process problems start making noise. Many of them come from startup conditions, such as low suction levels, partly open valves, or wrong valve line-ups.

  • Pump cavitation: Cavitation sounds like gravel or crackling in the pump casing. It often means low suction pressure or a restricted inlet.
  • Recirculation: A pump running far from its best efficiency point can produce random, surging noise.
  • Bypass and drain valves: Valves opened for warm-up are often left cracked. Contact-mode readings confirm they are closed and holding.
  • Control valves: Unusual hiss or chatter can point to wrong positioner settings after maintenance.

Cavitation is the rapid formation and collapse of vapor bubbles inside a pump. Record a reading at each critical valve and pump once the line reaches normal flow. These first readings under load become the most useful baseline you have.

Step 8: Scan Electrical Equipment Safely When You Re-Energize

Electrical faults such as corona discharge, tracking, and arcing produce ultrasound. Inspectors can often hear them through panel vents and door seals without opening energized equipment.

  • Scan after re-energization: Check switchgear, transformers, and motor control centers once they carry load again.
  • Listen for the signature: Corona gives a steady buzz, tracking gives an irregular crackle, and arcing gives sharp pops.
  • Keep doors closed: Scan from outside through gaps and vents to reduce arc flash exposure.
  • Confirm with other tests: Check suspect readings with thermography and electrical testing under your site's NFPA 70B and 70E practices.

Shutdowns often include cleaning, terminal re-tightening, and breaker work in electrical rooms. A quick ultrasound commissioning scan on startup confirms that work did not leave a new fault behind.

Ultrasound vs Vibration vs Thermography During Startup

Ultrasound vs vibration analysis vs thermography comparison during startup | Cryotos

Ultrasound commissioning is not the only startup check, and it works best alongside the others. The table shows where each method fits during commissioning after a shutdown.

MethodBest Startup UsesStrengthLimitation
UltrasoundLeaks, steam traps, valve leak-by, lubrication, electrical arcingDetects faults early, works in noisy plants, often without opening equipmentNeeds a baseline and trained ears; limited on liquid leaks
Vibration analysisMisalignment, imbalance, looseness, bearing defects on rotating machinesDetailed diagnosis of mechanical faultsWeaker at low speeds; needs more setup time per machine
ThermographyElectrical hot spots, insulation gaps, trap backup, overheating bearingsFast visual scan of large areasNeeds load and time for heat to build; affected by emissivity

Use ultrasound first for speed, then call in vibration and thermography to confirm and size the problems it finds.

Sample Ultrasound Commissioning Register

A simple register keeps every ultrasound commissioning reading tied to an asset, a window, and an action. The example rows below are illustrative; build your own limits from site data.

AssetWindowBaseline (dB)Startup (dB)FindingAction
Pump P-201 drive-end bearingFirst run18279 dB rise, dry toneGrease by ear, re-test in 24 h
Isolation valve V-114During isolationUpstream 22Downstream 34Likely passingProve isolation by procedure; raise repair
Steam trap ST-36Warm-upCyclingConstant rushBlowing throughCorrective work order
Flange F-12 on nitrogen headerRe-pressurizationQuietAudible rushGasket leakRe-torque, re-scan
MCC-3 incoming sectionRe-energizationQuietSteady buzzPossible coronaThermography and electrical test

Keep the same test points and settings for every entry, so later readings can be compared directly.

Step 9: Record New Baselines and Turn Findings into Work Orders

A startup reading is only valuable if someone acts on it and can find it later. Close every ultrasound commissioning finding with an owner, a deadline, and a stored result.

  • Raise a work order per finding: Use work order management to assign each leak, trap, bearing, or electrical finding with photos and readings attached.
  • Save the clean startup as the new baseline: Readings from healthy assets after startup become the reference for future routes.
  • Link readings to the asset: Store dB values against each asset record, so trends build over time.
  • Review at the next shutdown: Use this startup's findings to plan the next shutdown's work list.

A Computerized Maintenance Management System makes this practical. Technicians scan a QR tag, enter readings on mobile, and raise a request on the spot. With condition monitoring software, readings can also flow in from connected sensors. Maintenance teams using Cryotos have reported up to 30% reduction in unplanned downtime and 25% faster repair turnaround.

The goal is simple: every startup should leave you with better data than the last one.

Frequently Asked Questions About Ultrasound Commissioning

What can ultrasound detect during startup after a shutdown?

Ultrasound can detect gas and steam leaks, failed steam traps, passing valves, under- or over-lubricated bearings, pump cavitation, and electrical corona, tracking, or arcing. These faults create high-frequency sound that the instrument picks up before many of them show up as heat or vibration.

When should we take ultrasound baselines before a shutdown?

Take baselines in the days just before the shutdown, while assets run at normal speed, load, and temperature. Use the same test points and instrument settings you will use after startup, so the readings can be compared directly.

Can ultrasound prove that an isolation valve is holding?

Ultrasound can show whether a valve sounds like it is passing, which is useful evidence. It does not replace your lockout/tagout procedure, so always prove isolation using the methods your site requires before work starts.

What frequency should I use for ultrasound commissioning checks?

Many inspectors use around 38 to 40 kHz in airborne mode for leaks and electrical scans. For contact checks on bearings, valves, and steam traps, settings around 25 to 30 kHz are common. Follow your instrument maker's guidance and keep settings consistent.

Can ultrasound replace vibration analysis during startup?

No. Ultrasound is faster and better for leaks, traps, lubrication, and electrical checks, while vibration analysis gives deeper diagnosis of misalignment, imbalance, and looseness. Most plants use ultrasound to screen and vibration to confirm.

How does a CMMS support ultrasound commissioning?

A CMMS stores baselines against each asset, puts startup checklists on technicians' phones, and turns findings into tracked work orders. That keeps every reading, photo, and repair in one record for the next shutdown.

A clean restart is one where every leak, trap, bearing, and panel has been heard and recorded. Schedule a free demo to see how Cryotos turns your ultrasound commissioning readings into baselines, work orders, and a startup record you can trust.