How to Configure Shift Calendar Holidays: Exclude and Include Days for MTTR and MTBF

Calendar
Duration:
12 min
calendar today
Published on
September 28, 2026
Featured Image

Shift calendar holidays are the exclude and include overrides on a location's shift calendar. They mark specific dates as non-working or extra-working, so MTTR and MTBF count only the days a machine was actually scheduled to run. They sit on top of the base weekly pattern. That pattern sets the working days, number of shifts, and shift timings for a financial year period. Shift calendar holidays adjust that pattern one date at a time.

Most Computerized Maintenance Management System (CMMS) platforms get the base pattern right and stop there. That leaves every declared holiday, plant shutdown, and compensatory working Sunday counted as a normal working day. Every MTTR and MTBF figure built on that count comes out wrong. This guide walks through how to exclude and include those dates, step by step. The goal: an available-days count that matches what actually happened on the shop floor.

Key Takeaways

  • Exclude removes a day: It pulls a declared holiday or shutdown date out of available days, even if it falls on a normal working day.
  • Include adds a day back: It credits a compensatory working day, such as a worked Sunday, into available days, even if it falls on a normal off day.
  • Overrides sit above the base pattern: The weekly working-day pattern stays the source of truth; exclude and include only adjust specific dates.
  • Order matters: Exclude, then include, then confirm the resulting count before trusting any MTTR or MTBF report.

What Are Shift Calendar Holidays?

Shift calendar holidays as exclude and include overrides on the base weekly pattern | Cryotos

Shift calendar holidays are the exclude and include overrides on specific dates in a location's shift calendar. They sit on top of the base weekly pattern. That pattern sets the working days, the number of shifts, and each shift's start and end time for a financial year period. Shift calendar holidays fix that pattern for the dates that don't follow it.

A location's calendar might say Monday to Saturday, two shifts, April to September. That pattern alone can't flag the 15th of August as a national holiday. It also can't flag a Sunday in October as a working day, even if the plant ran a catch-up shift that day. Exclude and include days capture exactly those two exceptions.

How This Differs from the Base Weekly Pattern

The base weekly pattern is set once per location and financial year period. It answers one general question: which days of the week does this site normally run? Shift calendar holidays answer a narrower question, for a single date: does this day break that general rule? Asset management standards such as ISO 55000 judge an asset's reliability against planned running time, not total calendar time. Exclude and include days protect exactly that distinction.

That distinction matters for a reason. A base pattern change should apply going forward only. A single excluded or included date is a one-time exception. Mixing the two causes problems: editing the base pattern to handle one holiday reclassifies every future week, not just that one day.

Exclude vs. Include Days: What's the Difference?

Exclude and include days are the two moves inside shift calendar holidays. Both change the available-days count for a period, but they move it in opposite directions, and they apply to opposite situations.

FactorExclude a DayInclude a Day
What it doesRemoves a normally working day from available daysAdds a normally off day into available days
Typical use caseNational holiday, company holiday, planned shutdownCompensatory working Sunday, festival make-up day, catch-up shift
Effect on MTBF denominatorLowers planned operating time for the periodRaises planned operating time for the period
Effect on MTTRStrips non-working clock hours from any breakdown spanning the dateCounts the date's shift hours normally for any breakdown that day
Base pattern touched?No, only that date is flaggedNo, only that date is flagged

Neither override changes the base weekly pattern itself. That's what makes them safe to apply. Every other week in the period stays untouched.

How to Configure Shift Calendar Holidays in 4 Steps

Four steps to configure shift calendar holidays: base pattern, exclude, include, recalculate | Cryotos

Configuring shift calendar holidays follows the same four steps every time. That's true whether you're setting up a new site or adding one holiday to an existing calendar.

Step 1: Set the Base Weekly Pattern and Financial Year Period

Before adding any override, confirm the base pattern is correct. Check the working days, the number of shifts, and each shift's start and end time for the financial year period you're configuring. The financial year period is the From and To month range a shift pattern applies to. That's what lets one location run two shifts from April to September, then three shifts from October to March.

Get this base pattern right first. Every exclude or include date you add later is measured against it. A wrong base pattern makes every override wrong too.

Step 2: Mark Excluded Dates for Holidays and Shutdowns

An excluded date is a calendar day removed from available days for a period, regardless of the base weekly pattern. List every declared holiday, regional observance, and planned shutdown day for the period. Then flag each one as excluded on the location's calendar. These are the same dates covered by a region's official public holiday calendar.

  • National and regional holidays: Dates set by the location's region. These differ site to site in a multi-location setup.
  • Company-declared holidays: Dates the organization closes even though they aren't public holidays, such as a founder's day or a local festival.
  • Planned shutdowns: Full-plant shutdown days for annual maintenance or a production pause, even mid-week.

A shutdown with technicians still on-site needs a second decision, covered in the mistakes section below. Exclude the day from MTBF's operating-time base. But don't strip the technicians' own work-order timestamps from MTTR.

Step 3: Mark Included Dates for Compensatory Working Days

An included date is a calendar day added to available days for a period, regardless of the base weekly pattern. List every date that breaks the pattern the other way: a normally off day where the location actually ran. Flag each one as included.

  • Compensatory working Sundays: A Sunday worked to make up for a mid-week holiday.
  • Festival make-up days: A normally off day worked because production shifted around a regional festival.
  • Production catch-up shifts: An extra working day added for a demand spike or a delayed order.

Skip this step, and a machine that ran on an included day gets no credit for that exposure in its MTBF. Any breakdown that day also gets pushed into an undefined "outside shift hours" bucket, instead of its normal shift.

Want to see the effect of a single override before changing your live calendar? Try the free Cryotos MTBF calculator with and without a holiday excluded from the period.

Step 4: Recalculate Available Days for the Period

Once every exclude and include date is flagged, you can calculate the available-days count for the period. Take the base working days in the range. Subtract the excluded dates. Add the included dates. That final number feeds planned operating time for MTBF. It also defines which clock hours count toward MTTR for any breakdown in the period.

Check this number against the production calendar before you trust any report built on it. A mismatch here is one of the most common reasons MTTR and MTBF figures don't match what the shop floor experienced that month.

How Excluded and Included Days Affect MTTR and MTBF

The available-days count from Step 4 feeds directly into both metrics. But it changes each one through a different mechanism.

Effect on MTBF

Planned operating time is shift hours multiplied by available days in the period. Excluding a holiday removes its hours from that total. Including a compensatory working day adds them back. A lower operating-time base, with the same failure count, gives a lower, more accurate MTBF. A higher base, from a skipped exclusion, inflates it. Reliability engineers use this same exposure logic when they calculate availability.

Take a single-shift location running an 8-hour shift. It has 26 base working days in a month. One national holiday falls on a working day. The month also had 6 hours of breakdown downtime across 4 failures.

MetricWithout Excluding the HolidayAfter Excluding the Holiday
Available days2625
Planned operating time208 h200 h
Breakdown downtime6 h6 h
Breakdowns44
MTBF50.5 h48.5 h

One missed exclusion inflated this location's MTBF by about 4%. A calendar with several unflagged holidays and shutdowns compounds that gap across every reporting period. This is exactly why shift calendar holidays exist: to keep planned operating time honest.

Effect on MTTR

MTTR isn't affected by the available-days count directly. But it is affected by which clock hours count while a breakdown is open. Say a breakdown starts before an excluded holiday and finishes after it. That excluded day's non-working hours should be stripped from the elapsed repair time. It's handled the same way as a weekend or an overnight gap. An included compensatory working day works the other way. It's a normal working day for MTTR purposes, so a breakdown that day is timed like any other shift, not treated as an exception.

Cross-check any shift's MTTR figure with the free MTTR calculator, once the excluded hours are removed from a breakdown's elapsed time.

The EIC Method: Exclude, Include, Confirm

The EIC method: Exclude, Include, Confirm available days for accurate MTTR and MTBF | Cryotos

The EIC Method: a three-step audit for reviewing shift calendar holidays before you trust an MTTR or MTBF report for a period.

  • Exclude: Confirm every declared holiday and shutdown day for the period is flagged as excluded. Don't just leave it as a note in an email or spreadsheet.
  • Include: Confirm every compensatory working day and catch-up shift is flagged as included. This gives the site credit for that exposure.
  • Confirm: Recalculate available days for the period. Check the result against the production calendar before the MTTR and MTBF report goes out.

Run the EIC Method once at the start of the financial year period. Run it again whenever a new holiday, shutdown, or catch-up shift is announced mid-period.

Common Mistakes When Excluding and Including Days

Most errors in shift calendar holidays setup come from a handful of repeated mistakes, not from the formulas themselves.

  • Editing the base pattern instead of adding an override: Changing the weekly pattern to handle one holiday reclassifies every other week in the period.
  • Excluding a shutdown day entirely, technicians included: The day should still be excluded from MTBF's operating-time base. But active work-order timestamps from technicians on-site should still count toward MTTR, for the work they actually did.
  • Forgetting regional differences in a multi-location setup: A holiday in one region isn't a holiday in another. Each location needs its own excluded and included dates.
  • Adding included days without an operating reason: An included day should represent a day the location genuinely ran. Including a day that didn't run just inflates available days for no reason.
  • Leaving mid-period overrides unconfirmed: Say an unannounced shutdown gets added after the fact, but never flagged. Every report between the shutdown and the fix stays wrong.

Each of these is a data-entry gap, not a formula problem. The four-step setup above closes them once. The EIC Method catches anything that slips through later.

How Cryotos Handles Exclude and Include Days for MTTR and MTBF

Cryotos ties shift calendar holidays directly to the same location shift calendar that feeds MTTR and MTBF. Flag a holiday or catch-up shift once, and the available-days count changes everywhere it's used, not just on one report.

  • Location-level overrides: Each site keeps its own excluded and included dates, on top of its own base weekly pattern and financial year period.
  • Automatic recalculation: Available days, and the planned operating time built from them, update the moment a date is flagged.
  • Shift-aware breakdown tagging: Every breakdown work order still carries the shift and date it started in, so excluded and included hours apply at the shift level, not just the day level.
  • Downtime tracking built in: Downtime tracking captures the stop and restore timestamps that MTTR and MTBF are built from. That gives the override layer accurate clock hours to work with.

Maintenance teams using Cryotos have reported up to 30% reduction in unplanned downtime and 25% faster repair turnaround. An accurate available-days count is part of what makes those figures trustworthy in the first place. The shift calendar sits on the same record as every asset under that location. That makes asset maintenance management software the one place to see how holidays and catch-up shifts actually moved a site's reliability numbers.

Frequently Asked Questions

What is the difference between excluding a day and including a day in shift calendar holidays?

Excluding a day removes it from available days. This applies even if it falls on a normal working day in the base weekly pattern, typically for a declared holiday or shutdown. Including a day adds it into available days. This applies even if it falls on a normal off day, typically for a compensatory working day or catch-up shift.

Does excluding a holiday make MTBF look better or worse?

Excluding a holiday usually lowers MTBF slightly. It removes hours from the planned operating time denominator without changing the failure count. That lower figure is the more accurate one. It reflects only the hours the asset was actually scheduled to run.

How should a breakdown that spans an excluded holiday be handled for MTTR?

The non-working hours inside the excluded date should be stripped from the elapsed repair time. It's handled the same way as a weekend gap. That way, MTTR reflects the technician's actual working time, not the full calendar span.

Can different locations have different excluded and included dates?

Yes. Each location keeps its own excluded and included dates on top of its own base weekly pattern. This matters for multi-site operations, where regional holidays and local production schedules differ from site to site.

Should a shutdown day with active maintenance work still be excluded?

The day should still be excluded from MTBF's operating-time base, since the asset wasn't in production. But work-order timestamps from technicians actively working during that window should still count toward MTTR, for the tasks they completed.

Getting exclude and include days right keeps MTTR and MTBF built on real operating time, not calendar time. Schedule a free demo to see how Cryotos applies your shift calendar holidays automatically, across every location's reliability report.

Want to Try Cryotos CMMS Today?

Get Free Demo

Let AI Take Control of Your Maintenance

Cryotos AI predicts failures, automates work orders, and simplifies maintenance—before problems slow you down.

Try AI-Powered CMMS
🡢